UniCompound Semiconductor Corporation
date:2018-01-26 browser:95
Project name: construction project about gallium arsenide and gallium nitride of UniCompound Semiconductor Corporation
Engineering site: No. 368, Hangang West Road, Hanjiang District, Putian City, Fujian Province
Construction unit: UniCompound Semiconductor Corporation
Building storey: three floors of wastewater plant, including 1 floor under the underground and 2 floors above the ground
Structure type: reinforced concrete and frame-shear wall stiffness structure
Reconstructive building area: 17,902.48 m2
Reconstructive building area: 17,902.48 m2
Awards: manufacturer with Excellent Management Award
Refrigerating machine and pipeline
Secondary distribution system pipeline